General Summary
Irrigation/Landscape Improvement Project
Wes Perryclear (Special Districts/LA County Parks and Recreation) provided the following updates and information to the committee:
The original completion date of the irrigation system will be extended in order to do additional repairs discovered during the course of the current renovation.
Landscape plans have been completed and bid documents are being processed. Handouts for the committee’s review included a proposed plant list for the upcoming landscape portion of renovation and the Landscape Planting Plan, which includes the scope of work to be used for bidding purposes.
Weather permitting planting is scheduled to begin around 3/1/2010.
New Maintenance Contract
Patrick Malekian (Special Districts Administrator/ LA County Parks and Recreation) proposed that the start date for the new landscape maintenance contractor, Rich Meier's Landscaping, Inc, begin 1/1/2010. The committee approved his proposal. American landscape will continue on a month-to-month basis until the new contractor’s start date.